Transforming D.E. Yardanou with Advanced Waterwork Technical Solutions
- Akcon

- Jan 15, 2024
- 1 min read
Updated: Feb 20, 2025
Emergency construction works to solve soil erosion due to excessive water drainage in D.E. Iardanou and specifically within the settlement of the local community of Prasinon. This is a closed water pipe, where the rainwater from the adjacent street collects, within the settlement of t.k. Prasino. The intervention that has been implemented includes the construction of a closed pipeline approximately 160 meters long, from prefabricated cement pipes with an internal diameter of D = 800mm. The above construction was done by placing the cement pipes on a layer of concrete class C 16/20. Before the work began, the slopes of the open ditch were cleaned.